Problem: Red Oak Sourcing’s server room required a commercial HVAC upgrade to keep the servers cool and protected. They wanted a slim, redundant system to ensure that the servers would stay cool in all weather conditions.
Solution: N.E.T.R., Inc. installed two Mitsubishi ductless air conditioning units in the server room, set to a lead-lag operating schedule that would protect the servers in-case of failure, extend the life of both units, and function in temperatures as low at -20 degrees.






Red Oak Sourcing in Foxborough, MA, is a large generic drug sourcing company that required an upgrade to their old Data Aire unit that had been installed in the server room back in the 1990s. The server room required year-round cooling due to the constant heat put out by the servers and the old AC system could not keep up in the colder months.
The server room at Red Oak Sourcing was a 15 x 10 space, located on the third floor of the building. The old Data Aire unit was removed, and two Mitsubishi ductless air conditioning units were installed on opposing walls. The piping for these units was then run up to the fifth floor to the condensers that were installed on the roof.
Is your business in need of an upgrade to an outdated commercial HVAC system? Do you find yourself unable to find the perfect temperature for your office because of a failing system? Contact N.E.T.R., Inc. today, and our heating and cooling specialists will work side-by-side with you to design the ideal heating and air conditioning system for your home or business.